The final design is complete with highlights including a family change room, lazy river in the Leisure Pool, ramp accessibility into all of the pools, open reception area and new fitness room.
Project Schedule Outline
Out to Tender Jan 17, 2017
Site Meeting Jan 31, 2017 (Pool Closed 11:30am – 1:30pm)
Close tender Feb 7, 2017
Tender award Mar 3, 2017
Pool Closed Mar 19, 2017
Estimated closure time is 8-9 months.
An updated Swim and Fitness Schedule for the time period from Feb 4-Mar 18 is now available on the Aquatic Centre Schedule section of the website. There are a few notable changes on this schedule.
For more information please contact Project Manager Floyd Mann at 250.615.3022.